Scope of work
Operational Challenges & Compliance Gaps
The CETP, treating 400 m³/day of tannery effluent, faced operational inefficiencies that hindered compliance with PCB discharge limits. Stratus was contracted to evaluate and improve system performance.
Process Optimisation & Staff Training
Stratus conducted a detailed process audit, identifying bottlenecks in coagulation, sedimentation, and biological treatment. Key interventions included:
- Optimising sludge settling and aeration cycles
- Adjusting chemical dosing for better efficiency
- Training on-site operators for better plant management
Capacity Expansion Planning
A cost analysis was prepared to scale the CETP from 400 m³/day to 1000 m³/day, ensuring future sustainability and compliance with stricter discharge norms.