You are viewing the website for Stratus India

Case Studies

CETP Operation & Optimisation – Madhavaram, Chennai

Operational Challenges & Compliance Gaps

The CETP, treating 400 m³/day of tannery effluent, faced operational inefficiencies that hindered compliance with PCB discharge limits. Stratus was contracted to evaluate and improve system performance.

Process Optimisation & Staff Training

Stratus conducted a detailed process audit, identifying bottlenecks in coagulation, sedimentation, and biological treatment. Key interventions included:

  • Optimising sludge settling and aeration cycles
  • Adjusting chemical dosing for better efficiency
  • Training on-site operators for better plant management

Capacity Expansion Planning

A cost analysis was prepared to scale the CETP from 400 m³/day to 1000 m³/day, ensuring future sustainability and compliance with stricter discharge norms.

Scope of Work

  • Phase I ESA
  • Phase II Site Investigation